Project Manager: Fernando Canon - (951) 827-4821

Planner: Melissa Garrety - (951) 827-7376


Project Description

Renovate the existing space in the Orbach library basement to create a clinical skills and simulation suite, which will serve the School of Medicine program.

Anticipated Construction Start: April 2020

Anticipated Construction Completion: February 2021
 

The finished project will develop updated Library office/administrative spaces, a new SOM student/faculty/staff lounge space, and Clinical Skills suite, including mock exam rooms, ER/ICU simulation spaces and support spaces. This is a major renovation that will involve removal/modification/installation of demising walls, flooring, lighting, mechanical systems and casework.

Project Activity

Current Activity

  • Subcontractos bidding

Next Steps

  • Start Construction

Construction Notices

  • N/A
SOM CSSS Work Area

SOM CSSS Timeline

SOM CSSS Timeline

SOM CSSS Construction Updates

  • Construction Alert #1

    954044 COM CSSS Construction Alert #1

    Please be advised that the following activities will be occuring from 6:30am to 3:30pm on the Orback Library site and adjacent areas week of May 4th.

    • Building construction barricades and door in the corridors leading to the loading dock
    • Cover all other non-construction doors with visqueen and zipper for dust control
    • Deliver temporary bathrooms and hand washer to the Construction site
    • Setup Kitchell team office area

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #2

    954044 SOM CSSS Construction Alert #2

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of May 11th.

    • Safe-Off Coordination Meeting
    • Deliver temporary bathrooms and hand washer station to the Construction Site.
    • Setup Kitchell team office area.
    • Electrical Safe-Off
    • Temp Power/Lighting
    • Demo Furniture, ACT Tiles and 2 Walls

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project

     

  • Construction Alert #3

    954044 SOM CSSS Construction Alert #3

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of May 18th.

    • Deliver temporary bathrooms and hand washer station to the Construction Site.
    • Electrical Safe-Off
    • Temp Power/Lighting
    • Demo Furniture, ACT Tiles and 2 Walls

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #4

    954044 SOM CSSS Construction Alert #4

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of May 26th.

    • Deliver temporary bathrooms and hand washer station to the Construction Site.
    • Identify utilities for Demo
    • Safe Off/Cut and Cap Mech/Elec
    • Safe Off/Cut and Cap Plumbing
    • Demo MEP
    • Temp Power/Lighting

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #5

    954044 SOM CSSS Construction Alert # 5

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of June 1st.

    • Demolition of Flooring and Ceiling Grid
    • Safe Off Electrical
    • Provide Temporary Power/Lighting
    • Cut and Cap HVAC Ductwork and Provide Temporary Cooling
    • Mark/Identify all HVAC lines to be Demoed or Remain, Electrical lines to be Demoed or Remain, Plumbing to be Demoed or Remain, and Fire Sprinkler lines to Remain
    • Demo Walls and MEP

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

     

  • Construction Alert #6

    954044 SOM CSSS Construction Alert #6

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of June 8th.

    • Safe Off Electrical
    • Provide Temporary Power/Lighting
    • Mark electrical lines to be demoed and remain
    • Install filters for return HVAC lines
    • Miscellaneous demolition
    • Survey the site

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #7

    954044 SOM CSSS Construction Alert #7

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of June 15th.

    • Safe Off Electrical
    • Install filters for return HVAC Lines
    • Provide Temporary Power/Lighting
    • Mark electrical lines to be demoed and remain
    • Demo  Walls/Hard Lid Ceiling
    • Cut/Cap Mech. Ducts
    • Demo Ductwork
    • Demo Plumbing Lines
    • Layout Plumbing Trench
    • Saw cut/Demo Plumbing Trench

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #8

    954044 SOM CSSS Construction Alert #8

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of June 22nd.

    • Demo  Walls/Hard Lid Ceiling
    • Cut/Cap Mech Ducts
    • Demo Ductwork
    • Mark plumbing lines to be demoed and remain
    • Demo plumbing lines
    • Re-route plumbing lines to remain (RFI)
    • Layout Plumbing Trench
    • Sawcut/Demo Plumbing Trench
    • Excavate Plumbing Trench
    • Install plumbing Rough-Ins

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #9

    954044 SOM CSSS Construction Alert #9

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of June 29th.

    • Demo Fire/Smoke Alarms and Pull Station
    • Demo Electrical
    • Saw cut plumbing trench and break out concrete
    • Excavate plumbing trench
    • Relocated conduit for Stair 1 Emergency Lighting
    • Remaining demo post RFI responses (wall)

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.

  • Construction Alert #10

    954044 SOM CSSS Construction Alert #10

    Please be advised that the following activities will be occurring from 6:30AM to 3:30PM on the Orbach Library site and adjacent areas week of July 6th.

    • Saw Cut and Demo concrete for plumbing trench
    • Demo Fire/Smoke Alarms (Construction Site Only)
    • Remove and relocate existing electrical

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The team recognizes that construction activities will at times pose inconveniences and disruption to the staff located within the library and surrounding areas. We thank you for your patience during construction of this project.